Dear All,

Recently i have a faced one issue where i required to change TR status from released to unreleased.

I have assumption that once we released TR(task) then we can not revert TR to modiable, but that was wrong.

SAP have provided program using which we can do this.

Initially TR was in Released status.

Step 1: Go to SE38-> enter program name : RDDIT076 -> execute

Change released task to unreleased/ modifiable

Step 2: Enter TR/Task which status you want to convert from released to modifiable -> execute program

Change released task to unreleased/ modifiable

Step 3: you will find TR with R (Released) status.

Change released task to unreleased/ modifiable

double click on R status(encircled in above screen), you will find below screen where need to edit R status to D status(D= Modified).

Change released task to unreleased/ modifiable

click on Save. -> exit from program

Step 4: go to Se01-> enter TR name, you will find TR in unreleased(modifiable) status.

Change released task to unreleased/ modifiable

Regards,

Hitesh