Exclude ‘AVAC’ partially in a AVACed SAP-PS project-Option(s)
-   Pre
 requisite/case:
- Business wants to budget(fund) and control spend
 only on part of project work in SAP PS
- Project has one top WBS Element and multiple
 branches of WBS underneath:- For ex:
- One branch for CAPEX and another for OPEX
- `First one budgeted and second one isn’t!
 
- One branch of WBS is for Global R&D Spend, second
 for Country R&D Spend and third for Local R&D Spend- first two are
 budgeted and last isn’t!
 
- One branch for CAPEX and another for OPEX
 
- For ex:
- Budget Profile- Availability Control(AVAC)
 active on budgeting
- Define budgeting tolerance limit for AVAC (ex: 100%-
 error)- It may be controlled at transaction level
 
- User status
 profile (for WBS Element)- With couple of statuses and one among them
 forbidding ‘Availability Control’ (that is preferably not initial status)- INIT – initial status
- NAVC- status that prohibits Business Transaction
 ‘AVAC’
- YAVC- status that permits ‘AVAC’
 
- For purpose of this document, user status ‘INIT’
 does not prohibit any business transaction
 
- With couple of statuses and one among them
- Project/WBSEs are obviously released
- Cost element(s) may or may not be exempted from
 AVAC
- Steps:
- Create and Release Project structure
- Project may have:
- 1 Level 1 WBS Element (WBSE),
- 3 Level2 WBS Elements and
- multiple Level3 WBS Element under each Level 2
 WBSE
- A WBS branch is defined as one level 2 WBSE with
 its subordinate WBSEs
 
 
- Project may have:
- Budget one branch of WBS
- AVAC automatically activated for entire project
- Note: AVAC activation is at Proj Def level
 
- System sets status BUDG automatically on the
 budgeted WBS Element as well parent WBS Elements
- Now set the user status (NAVC) on the level 1
 (parent) WBS Element. Don’t choose
 ‘set and pass on’ option while setting the status
- Also set the user status (NAVC) on the level 2
 WBS element for the branch that should be excluded from availability control.
 Here you may choose to ‘set and pass on’ option
- Any commitment/actual posting (of course depending
 on other config.) will not fail on account of AVAC in the branch of WBS with user
 status NAVC
- Any commitment/actual posting will fail in the Availability
 controlled branch of WBS with user status INIT or YAVC
Alternate option:
- Configure the user status profile with initial
 status prohibiting ‘AVAC’. In this case, no WBS Elements will be protected by ‘AVAC’
- So User has to remember to set the User status
 permitting ‘AVAC’ to control project spend. If not, spend may exceed budget!